     Construction method of insulation rock wool board

insulation-rock-wool-board

     1. Draw the control line and hang the baseline
     1.1 Arrange the lines from the highest point and make a node every three floors to make the wall vertical;
     1.2 , Draw the horizontal and vertical control lines of the window on the wall, according to the building facade design and external thermal insulation technical requirements 
     1.3 Hang vertical datum lines at the large corners (inside corner and exposed corner) of the outer wall of the building and other necessary places, and hang horizontal lines at appropriate positions on each floor to control the verticality and flatness of the insulation rock wool board
     2. Bonding mortar
     2.1 Use specialized mortar mixer to mix the adhesive and surface glue powder according to the mixing ratio; the mixing time should not be less than 5 minutes, and the mixing must be sufficient, uniform, and moderate in consistency;
     2.2 In the process of mixing mortar, it is not allowed to add any form of additives such as cement, quick-setting agent, antifreeze, filler, and color.
     Next issue we will continue to introduce construction method of insulation rock wool board. Please stay tuned.
【Tag of this article】:insulation rock wool board
【Editor】:CCEWOOLall rights reserved:Please indicate the source
  • Oversea Office

    CCEWOOL Thermomax Inc. T: +(1)4167359078 E: rockwool@ccewool.com Add: 341 Talbot St, London, ON N6A 2R5

  • Customer Service

    Tel:+86-533-7986860 Fax:+86-533-6077229 service@ccewool.com

  • Factory

    Zibo Double Egret Thermal Insulation Co.,Ltd Add: Minying Industrial Park Development Zone Zibo Shandong China,255000

CCEWOOL

SitemapCopyright ©CCEWOOL. All rights reserved.CNZZTechnical Support:NSW